Process 7 of 7

Closing a Project

Providing a fixed point to confirm acceptance.

Objectives

  • Verifying customer acceptance of products.
  • Ensuring that the user side can maintain the product.
  • Reviewing the performance of the project
  • Assessing the Benefits.
  • Addressing all open issues and risks.

Roles and Responsibilities

Corp. Or Prog. Mgmt

Approve Benefits Review Plan, Lessons Report.

Executive

Approves Follow-on Action Recommendations, Acceptance Records, End Project Report, Draft Project Closure Notification; Review Benefits Review Plan, Lessons Report.

Senior User

Approves FAR, AR, EPR, DPCN; Review BRP, LR.

Senior Supplier

Approves FAR, AR, EPR, DPCN; Review BRP, LR.

Project Manager

Creates FAR, EPR, LR, DPCN; Obtain AR.

Project Assurance

Review documents; advise PM.

Project Support

Create Product Status Account, Update Configuration Item Records.

Applying the Themes

Business Case (Why)

Business Case and Benefits Review Plan are updated.

Organisation (Who)

Inform the stakeholders, create Draft Project Closure Notification.

Quality (What)

Confirm that acceptance Criteria have been met. Close the Quality Register.

Plans (How, How much, When)

Review and update the Project Plan.

Risk (What if)

Close the Risk Register.

Change (What is the impact)

Update and close the Issue Register.

Progress (Where are we, direction, should we carry on)

Confirm the product is delivered as defined, create Follow-on Action Recommendations, Lessons Report, End Project Report; review Project Initiation Documentation; close Lessons Log.